What a planning approval tells a battery supplier
Nine Mile Energy Park · Victoria, Australia · Pacific Green
Two stages. Different storage requirements.
Approved project stages | Stage | Power | Energy | Duration |
| 1 | 250 MW | 500 MWh | 2 hours |
|---|
| 2 | 250 MW | 1,000 MWh | 4 hours |
Planning permits granted 28 May 2026. Procurement availability must be established separately.
Build a better-qualified shortlist
Research implication: a named developer, approved stages and different duration requirements give a supplier specific points to investigate.
Next check: ask who is buying, which specifications apply and whether supplier selection remains open.
Planning approval does not establish an open tender or an available contract.
The developer states that a grid connection agreement is still required. A project page in the product shows the date of its information.