Worked example: a battery project in Victoria

This example uses only public information. It shows how a planning approval is read. It is not a BESS Intelligence page.

Where to go next

What a planning approval tells a battery supplier

Nine Mile Energy Park · Victoria, Australia · Pacific Green

Two stages. Different storage requirements.

Approved project stages
StagePowerEnergyDuration
1250 MW500 MWh2 hours
2250 MW1,000 MWh4 hours

Planning permits granted 28 May 2026. Procurement availability must be established separately.

Build a better-qualified shortlist

Research implication: a named developer, approved stages and different duration requirements give a supplier specific points to investigate.

Next check: ask who is buying, which specifications apply and whether supplier selection remains open.

Planning approval does not establish an open tender or an available contract.

The developer states that a grid connection agreement is still required. A project page in the product shows the date of its information.

Worked example from public filings · checked 5 November 2026. Illustrates the research approach; not a product export.