# Worked example: a battery project in Victoria

> A worked example from public information: what a planning approval for a Victorian battery storage project tells a battery supplier.

Canonical: https://metagnition.com/bess-intelligence/examples/nine-mile/
Last updated: 2026-11-24

This example uses only public information. It shows how a planning approval is read. It is not a BESS Intelligence page.

## Where to go next

- [How BESS Intelligence research works](https://metagnition.com/bess-intelligence/methodology/): Where the information comes from, dates and fields not stated.
- [Projects](https://metagnition.com/bess-intelligence/project-tracker/): The module this example relates to.
- [EPC and integrators](https://metagnition.com/bess-intelligence/epc-and-integrators/): The EPC line on a project page.

## What a planning approval tells a battery supplier

Nine Mile Energy Park · Victoria, Australia · Pacific Green

### Two stages. Different storage requirements.

| Stage | Power | Energy | Duration |
| --- | --- | --- | --- |
| 1 | 250 MW | 500 MWh | 2 hours |
| 2 | 250 MW | 1,000 MWh | 4 hours |

Planning permits granted 28 May 2026. Procurement availability must be established separately.

### Build a better-qualified shortlist

Research implication: a named developer, approved stages and different duration requirements give a supplier specific points to investigate.

Next check: ask who is buying, which specifications apply and whether supplier selection remains open.

Planning approval does not establish an open tender or an available contract.

The developer states that a grid connection agreement is still required. A project page in the product shows the date of its information.

Worked example from public filings · checked 5 November 2026. Illustrates the research approach; not a product export.